Notable Projects

Owner/Engineer Year Contract Value Project Description Contact
SNC Lavalin/Fluor Constructors
@I.O.L.
1999/2000 $920,000 HUIS Civil/Concrete R. Belanger
A. Mockler
SNC Lavalin/Fluor Constructors
@I.O.L.
1999 $725,000 LVIS II Civil/Concrete J. McMahon
C. Tatarin
Dow Chemical 1999 $400,000 Erosion Protection Brine Pond 431 & Firewater Pond R. Kameka
Nova Styrene II 1998 $800,000 Control House Addition P. Matthews
Nova Styrene II 1997/1998 $2,500,000 Foundations & Sewers Styrene II Expansion P. Matthews
Shell/Kilborn 1996/1997 $1,250,000 Foundations & Underground Services No. 1 Crude Bjarne Pederson
Dow Chemical 1995 $297,000 Installation of Clean Water Sewers L. Blondin
Terra 1995 $795,000 Urea Liquor Plant Expansion S. Poskorowski
Bayer/Polysar 1995 $292,000 I-Plant Secondary Cooling Project H. Whitton
W.Wiarda
Nova Corunna/Octagon Engineering 1993 $425,000 C-5 Diene Foundations and Concrete Paving D.Bothwell
Ethyl Chemical 1992 $375,000 Environmental Water Enhancement M.L. Kirk
R.D. Sonnier
Esso Petroleum 1991 $466,000 Loading Rack and Weigh Scales Project Winston
Cameron
Dow Chemical 1989/1990 $642,000 Firewater Line Replacement I.McKinley
Ellis-Don@Dow Chemical 1986 $381,000 Excavation for Dow Modeland Building P.Mychaluk
George Wimpey Canada Limited CIL Ammonia II Phase 2 1984 $420,000 Weigh Scale Building, Roads and Earthwork for R/R C. Calvert
Alec Hutchinson
Associated-Kellog Limited @ Shell Canada 1983 $480,000 Foundations for Cat Cracker Upgrading G.R. St. Mitchell
W. Pichard
Sheaffer Townsend @ Ammonia II Project 1982/1983 $520,000 Foundations, U/G Piping, Grouting Don Beatty
Bechtel Canada/CIL Ammonia II Project 1982/1983 $950,000 Foundations, Concrete Paving and Earthwork B.K. Stevens
D. Kirkland
Acres Davy McKee Polysar I-Plant 1981 $1,150,000 Foundations, Grading, Paving and Fireproofing